Douglas Pharmaceuticals NPD Pilot Plant Facility

About the Project
This project included construction of a three-storey building comprising of labs, office, and warehouse space.
The new building was an extension to the Douglas Pharmaceuticals’ existing head office, labs, research and warehousing facilities, which remained operational throughout construction.
With the new build linking into the existing facility, close communication with the client was a regular occurrence to ensure our works did not impact their daily operations.
GBD Investments Ltd
Client
June 2021
Completed
Auckland
Location

The project involved the construction of a specialist pilot plant facility which is to be used in the research and development of new pharmaceutical products.

The scope includes an extension to an existing pharmaceutical facility, including head office where the facility remained operational throughout the construction phases, with close communication required on site with Douglas Pharmaceutical staff.

The predominant operational and logistical challenges to the project were during the early stages of the Covid-19 Level 4 Lockdown in March 2020, which meant that no staff could be on site at this time. Leighs Construction’s Health and Safety plans were updated and constantly monitored throughout the project, following the Ministry of Health protocols to mitigate risk.

Related Projects
Fisher & Paykel Healthcare, Building 4, Daniell Building
A 53,000m² concrete and steel mixed-use building with 5 laboratories, a manufacturing facility, distribution centre, and two model shops, two cafeterias, and a large open-plan office space with seven light wells to house large trees & water features.
University of Otago - Science Precinct Laboratory Redevelopment
The 6500m² of primarily science laboratories has been remodelled and refurbished to the highest scientific standards, housing a “super-lab” on the ground floor, with further laboratories, improved airflow/ventilation and additional floors.



.jpg)